Temple Health
HBO Pharmacy Upgrades
This project consisted of upgrading the existing facility pharmacy in the basement of pavilion park building to bring it up to date with USP regulation requirements. This project provided sterile compounding areas and a negatively vented hazardous pharmacy. A challenge through this project was coordinating with the materials management team and existing pharmacy since the space surrounding it was occupied and in heavy usage. To achieve an efficient layout for improved workflow, the adjacent areas were also impacted. This included the removal of an existing walk-in refrigerator which was quite a challenge to coordinate and execute.
Quick Facts
Location: Philadelphia, PA
Size: 1,300 SF
Schedule: 8 Months
Architect: Stantec Architecture & Engineering, LLC